The ruling clears the Port of South Louisiana to continue work on a Mississippi River deepwater terminal that would serve Hyundai and POSCO’s $5.8 billion steel plant in Ascension Parish.
RESERVE, La. (November 20, 2026) — The Port of South Louisiana can resume work on the Ascension Riverplex Megadock after a court dismissed a lawsuit seeking to halt the project. The dismissal ended a temporary restraining order that had paused the port’s work on the proposed deepwater dock and marine terminal.
According to the port, the court granted its motion to dismiss the lawsuit at a Tuesday hearing, finding that the port had acted properly. The Port of South Louisiana Commission plans to hold a public hearing and consider proposed financing for the riverfront infrastructure at an upcoming meeting.
“This ruling reinforces what we have maintained throughout this process: the Port of South Louisiana acted properly and in accordance with its responsibilities,” said Julia Fisher-Cormier, executive director of the Port of South Louisiana.
Deepwater terminal would support $5.8 billion steel plant
The Port of South Louisiana plans to build the dock and marine terminal on the west bank of the Mississippi River to serve Riverplex MegaPark. Hyundai and POSCO’s joint venture is building a $5.8 billion steel manufacturing plant at the industrial park. The plant is expected to create more than 1,300 direct jobs. Louisiana Economic Development’s steel plant announcement
The terminal would give the steel plant access to deepwater shipping. The port expects the public marine infrastructure to also support existing industries and future development along the river’s west bank.
Port proposes up to $400 million in revenue bonds
The port is considering issuing up to $400 million in revenue bonds to finance construction of the deepwater dock and related marine infrastructure. Under the proposal, the bonds would be repaid solely with revenue from the port’s lease of the dock to Hyundai-Posco Louisiana Steel.
The proposed financing will come before the commission as the port resumes work on the project.